Grand Park is located in Downtown Los Angeles. Grand Park stretches from The Music Center on the west to City Hall on the east. Blocks one and two of Grand Park, from Grand Avenue to Hill Street, will be open to the public on July 28, 2012, with blocks three and four of the park opening in Fall 2012.

The following activities will be taking place on the Grand Park Construction Site for the month of May 2012

Milestones Complete:

  • Grand Avenue ramps complete and open November 14, 2011.
  • Starbucks complete and open December 19, 2012.
  • Planting of plants in Block 1 complete March 26, 2012
  • Judges Ramp Open from Spring St. February 20, 2012
  • Planting of Block 2 complete April 30, 20

Fountain:

  • Fountain programming & commissioning ongoing during April and will complete in May
  • Punch list work has begun and will continue during May 2012
  • Review of Fountain programming by County end of April 2012
  • Fountain complete May 2012

Block 1

  • Trees & Plant material completed March 2012
  • Punch List nearing completion in block 1
  • Elevator building & Park management office will complete in May 2012
  • Elevator inspection and acceptance scheduled mid May 2012.
  • Punchlist of all planting block 1 to commence first week of May 2012.
  • Signage to be installed May 2012
  • Furniture to be installed May 2012

Block 2:

  • North & South promenades, roads, will complete in first week of May 2012.
  • Punchlist of block 2 to commence first week of May 2012.
  • Planting of block 2 completes end of April 2012
  • Punchlist of all planting for block 2 first week of May 2012
  • Signage to be installed May 2012
  • Furniture to be installed May 2012

Block 4: 

  • Park Services Building” completes mid May 2012.
  • Architectural concrete hardscape will complete second week of May 2012.
  • “A” permit work @ 2 promenade walks Spring St. first week of May 2012
  • Trees nearing completion of planting block 4 end of April 2012
  • Planting of plants and lawns to complete May 2012
  • Stainless rails and finishes, lights, etc… ongoing during May 2012
  • Signage to be installed May 2012
  • Furniture to be installed May 2012

Block 3:
 

  • Broadway terrace will complete pouring of architectural concrete May 2012
  • “A” permit sidewalks Broadway will complete first week May 2012
  • Trees nearing completion of planting block 3, and will complete first week of May 2012
  • Flagpoles in new Court of Flags will be installed last week of April.
  • Historical plaques to be installed as well as granite benches in May 2012
  • Signage to be installed May 2012
  • Furniture to be installed May 2012